In a ruling reported in January 2026, the Dubai Real Estate Court cancelled an off plan sale because the handover ran past the period agreed in the contract. It ordered the developer to refund AED 516,872, the instalment the buyer had paid, and to pay AED 100,000 for material and moral damages, plus court costs (Gulf News, January 2026). If your own handover keeps moving, this is what the routes to money back look like, and what each one needs from you.
By Umer Shauket, Founder & CEO, Cresco Real Estate. RERA ORN 34288. Published 25 November 2026.
We covered the basics, escrow, cancellation by RERA and the red flags, in Off plan delays: your rights and red flags. This piece is about getting compensated.
What waiting really costs
On 6 November a reader told The National he had paid 60% of an off plan price, the handover had slipped beyond 2026, and he was paying AED 135,000 a year in rent while he waited (The National, 6 November 2026). That is AED 11,250 for every month of delay. Rents are not falling fast enough to help much: the average Dubai rent was AED 77.3 per sq ft a year in September, still 5.5% higher than a year earlier, even though 21.4% of rental contracts in the third quarter were signed at a lower rent than before (Khaleej Times, 2 November 2026).
Three routes to money back
| Route | What it can get you | What it rests on |
|---|---|---|
| Settlement through the Dubai Land Department | A new dated completion, compensation, or cancellation and refund, agreed between both sides | Conciliation under Article 14 of Executive Council Resolution No. 6 of 2010; a settlement binds once DLD approves it |
| Court claim for damages | Compensation for the loss you can prove, which may include lost profit | UAE Civil Transactions Law, Articles 246, 292 and 295, read with your SPA |
| Cancellation and refund | The money you paid back, sometimes with damages | Court order, as in the case reported in January 2026 |
The legal points in the first two rows come from a UAE lawyer’s answers in Khaleej Times (May 2024 and September 2024). The same answers say a buyer can complain to the Dubai Land Department first or go straight to a Dubai court, and that whether rent you paid while waiting counts as damages is for the court to decide under your SPA. Where an agreement is terminated, Resolution No. 6 of 2010 requires the developer to refund retained amounts within one year of termination or 60 days after the unit is resold, whichever is earlier.
What a claim needs from you
A developer will point to two things: the grace period in your SPA, and force majeure, which Article 21 of Resolution No. 6 of 2010 allows as a defence. Whether the regional war that began on 28 February 2026 counts would be for a court; we found no published ruling on it. Our view of the wider risk is in Is Dubai safe right now?
So the claim rests on paper. Keep the SPA with its completion date and grace period, every payment receipt into the project escrow account, a monthly screenshot of the project’s progress on the Dubai Land Department’s Project Status service, every written promise of a new date, and your Ejari and rent receipts if you will claim rent.
Imagine the numbers
Imagine an AED 2,000,000 apartment. You have paid 60%, AED 1,200,000, and you rent at AED 135,000 a year. The handover slips 18 months past the grace period.
| Item | Amount |
|---|---|
| Rent paid during the 18 months | AED 202,500 |
| Damages in the January 2026 case, as a share of what that buyer had paid | About 19% (AED 100,000 on AED 516,872) |
Our arithmetic. The case is one ruling on its own facts, not a rate any court applies.
Our view: settle with paper, sue with proof
The common reaction to a delay is to stop paying or to threaten the developer. We think both weaken you. Keep paying into escrow unless a lawyer tells you otherwise, ask for a revised date and compensation in a signed addendum, and use DLD conciliation first. Go to court once the delay is past the SPA’s grace period and your costs are documented. That ruling shows a refund plus damages is possible, but it took a court to get there.
What this means for a buyer
- Find three lines in your SPA today: the completion date, the grace period, and what it says about compensation or termination.
- Start a delay file now, before you need it: receipts, progress screenshots, emails, rent receipts.
- Ask for every new date in a signed addendum, not an email or a call.
- Plan the cash. A late handover often lands when the final payment and fees fall due; our guide to the handover cash gap shows how to budget it.
- Check what is coming. Our view of handover risk in 2027 and 2028 explains why more projects may slip.
Honest limits
We are a brokerage, not a law firm, and this is not legal advice. The legal routes come from a lawyer’s published answers from 2024 and the January 2026 ruling as reported by Gulf News; the report names neither the developer nor the legal articles the court relied on. Contracts differ, and whether rent can be recovered depends on the court and your SPA. The worked example is hypothetical. Take your SPA and payment records to a property lawyer before you withhold any payment or file a claim.
Sources: Gulf News (January 2026); The National (6 November 2026); Khaleej Times (2 November 2026; May and September 2024); Executive Council Resolution No. 6 of 2010; UAE Civil Transactions Law.
Related on Cresco: Off plan delays: your rights and red flags · How to check a Dubai developer before you buy off plan